Documents - Russell House Group

Go to content
Russell House T168b Documents
Facade Inspections (May 2024)
Go to a plan of Russell House identifying the six elevations.
Go to a PDF showing specific defects on facades (1)
Go to a PDF showing specific defects on facades (2)
Go to a PDF showing specific defects on facades (3)
Windows
Window Inspections (May 2024)
Go to the Timber Condition RAG Visualisation 7 August 2024.
Window Inspections (May 2024)
Go to a plan of Russell House identifying the six elevations.
Elevation 1: Cambridge Street
Elevation 2: Gloucester Street
Elevation 3: Internal Charlwood Street side
Elevation 4: Alderney Street
Elevation 5: Charlwood Street
Elevation 6: Internal Gloucester Street side
Go to a PDF showing individual window inspections.
Go to a PDF showing specific defects on individual windows.
Windows
Go to a PDF of the Condition Survey Report prepared for WCC by Faithorn Farrell Timms LLP, dated 31 July 2021.
Client Briefs
Draft Client Brief (August 2024)
Go to a PDF of the final Draft Client Brief for the T168b project, issued for comment and feedback by 13 September 2024. The Works Value is £4.4m.
Client Brief (February 2023)
Go to a PDF of the Client Brief for the T168b project. This is the  version submitted to the WCC Programme Board in October 2023. The Works Value is £4.3 million.
Client Brief (April 2022)
Go to a PDF of the Client Brief for the T168b project. This is the first version of the stand-alone project for Russell House following separation from T168 (Churchill Gardens Phase 6). The Works Value is £3.1 million.
Current Status
Go to the page on the WCC website that describes the T168b project and its current status. This is updated regularly by WCC.
Roof
Go to a PDF of the Survey Report prepared for WCC by Bauder, dated 5 April 2022.
Fire Safety
Go to a PDF of the Fire Risk Assessment prepared for WCC by John Buckley, dated 5 January 2016.
June 2023 one-to-one sessions (1)
Letter from WCC (2 June 2023) to RH leaseholders notifying the latest cost estimated for T168b (£4,550,137). Invitation to one-to-one sessions.
June 2023 one-to-one sessions (2)
Go to a PDF of the summary update of the fire risk assessment, prepared by Kaivery Hislop (Client Surveyor) following the June 2023 leaseholder one-to-one sessions.
June 2023 one-to-one sessions (3)
Go to a PDF of the Q&As compiled by WCC (dated 4 October 2023) as an outcome of the one-to-one sessions.
Health & Safety - Scaffold Construction
Go to a PDF of the letter sent to RH residents about the crash deck scaffold, dated 8 September 2023.
Westminster meeting with residents October 2023
Go to a PDF of the agenda and paperwork issued by Westminster at the meeting on 25 October 2023.